Let,the total work is of x amount.

So,ken does x amount of work in 6 hrs

So,in 1 hr he will do x/6 amount of work.

Now,Barbie does x amount of work in 8 hrs

So,in 1 hr she does x/8 amount of the work.

Let,after working t hrs together the work will be finished.

So, in t hrs Ken does (xt)/6 amount of work and Barbie does (xt)/8 amount of work.

Clearly, (xt)/6 + (xt)/8 =x

Or, t/6 + t/8 =1

So, t=3.43 hrs

Mar 17, 2018

Detailed solution given so that you can see where everything comes from.

3" hours and "25 5/7" minutes"larr" Exact value"

3" hours and "26" minutes" to the nearest minute

Explanation:

People work at different rates. So the time taken by different people to complete a set amount of work will also be different. This is what we need to model

Let the total amount of work required to complete the task be W

Let Ken's work rate per hour be w_k
Let Barbie's work rate per hour be w_b
Let the total time working together be t

If Ken works on his own he can complete the whole task in 6 yours

"work rate "xx" time = work done.".............Equation(1)

color(white)("ddd")w_kcolor(white)("dddd")xxcolor(white)("ddd")6color(white)("d")=color(white)("ddd")W

So w_k=W/6 ...........................Equation(2)

If Barbie works on her own she can complete the whole task in 8 hours

Using the above method

w_b=W/8........................Equation(3)
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Consider Eqn(1) but combine the two work rates Eqn(2)+Eqn(3)

color(white)("d") (w_bxxt) color(white)("d")+ color(white)("d")(w_kxxt)=W

(W/8xxt)+(W/6xxt)=W

Factor out the t

t(W/8+W/6)=W

t((3W)/24+(4W)/24)=W

t(7W)/24=W

t=(24cancel(W))/(7cancel(W))

t=24/7" hours"

t=3 3/7" hours"larr Exact value

t=3" hours and "(3/7xx60)

t= 3" hours and "25 5/7" minutes"larr" Exact value"

Mar 17, 2018

3 3/7 hours or 3 hours and 26 minutes

Explanation:

First find out what fraction of the task they would each complete in 1 hour.

Ken will finish 1/6 of the task in 1 hour.

Barbie will finish 1/8 of the task in 1 hour.

If they work together, in one hour they will finish:

1/6 +1/8 of the painting task.

= (4+3)/24 = 7/24 is the fraction completed in one hour.

So to complete the whole task (24/24) we need to divide:

24/24 div 7/24

=24/24 xx24/7

=24/7 hours.

This simplifies to 3 3/7 hours

Which is easier given as 3 hours and 3/7 xx60 minutes

=3 " hours " and 25 5/7 minutes