10 men can build a house in 6 months, how many men would it take to build the house in 4 months?
2 Answers
Explanation:
This is an example of inverse proportion.
If the house is to be built in a SHORTER period of time, then MORE men will be needed.
As one quantity increases, the other decreases.
In an inverse proportion, the product of the two quantities will always give the same value, called the constant,
The first step is to find that constant, because then you can use it to find any unknown value.
We know that
How many men
On a higher level we have:
This assumes the additional men have the same capabilities and capacities as the first
Explanation:
We see that 10 men can build the house in
This is because
The time to do the work has become a fraction of what it was, so we will definitely need more men.
To calculate how many men we will need, we take the original number
But, before we do that, we need to tip over (invert) the fraction because we know as the time gets shorter, the number of men must increase. This relationship is called an inverse (like inverted) proportionality.
Then we have: